Workpackages

The project consists of eight workpackages. For easier orientation in our work it is necessary to know the abbreviation short names of the partner institutions.

  • WP1: Project management (NKP) December 2007 - November 2009
  • WP2: Preparation for system implementation and content enhancement (AIP) December 2007 - March 2008
  • WP3: Standardization of shared metadata (OUCS) December 2007 - October 2009
  • WP4: User personalization (MICF) February 2008 - October 2009
  • WP5: Personalization for contributors (AIP) February 2008 - November 2009
  • WP6: Multilingual and user friendly sophisticated access (SYS) December 2007 - November 2009
  • WP7: Evaluation, testing and validation (IMI) February 2007 - October 2009
  • WP8: Dissemination and Exploitation (BNE) December 2007 - November 2009